Project
Civil engineering project management
Department
Construction department
Business sector
Construction
Location
France
Duration
3 Months
Project's goals
OUR CLIENT IS A EUROPEAN LEADER IN THE FOOD INDUSTRY
DAO-BE construction division was acting as a project manager in order to supervized the Implementation of new sugar silos after dismantling and demolishing the old one and the concrete platform on which they were based.
DAO services for this project
This service allows DAO-BE to accompany his client to create a file with technical and graphical solution for the project.
-
Financial and technical pre-study
-
Specifications writing
-
Suppliers management
-
Construction project management until completion
Project' requirements
4 silos of 15m and 3,18m in diameter
There are 3 project phases :
- A first phase where two silos were implanted after we made a concrete platform (thickness of 142cm)
- A second phase where former 5 silos and platform are dismantled
- A third phase with the creation of a new plateform and installation of the two new silos and making a clean bitumen.
Final product